Production line installation at EVE Power’s Debrecen plant to begin in January 2027

Trial operation is planned for the second to third quarter of 2027, and 270–280 of the more than 400 permits needed for operation are already in place.

Published: Author: the editorial teamBusiness unit: NEST Comms2 min read

EVE Power Hungary’s annual review press conference on 24 November 2026
EVE Power Hungary’s annual review press conference on 24 November 2026. Photo: NEST Communications

On 24 November, our client EVE Power Hungary held its annual review press conference. The company called 2026 the year of partnerships. Its headcount has grown from 150 at the start of the year to almost 500, installation of the production lines begins in January 2027, and trial operation is expected in the second to third quarter of 2027.

In brief

  • On 24 November, our client EVE Power Hungary held its annual review press conference and called 2026 the year of partnerships.
  • Installation of the production lines begins in January 2027, with trial operation planned for the second to third quarter of 2027; the plant is being built for a capacity of 28 GWh and will produce 46-series cylindrical cells for BMW.
  • The investment is worth almost HUF 400 billion; the company currently employs 517 people, 90 per cent of them Hungarian.

Speaking at the press conference were Ádám Kovács, the company’s head of public affairs and government relations, and Dániel Kiss, external relations manager. Hu Tao, who was appointed managing director on 20 October, was unable to attend due to illness.

Where construction stands

A 210,000-square-metre building is going up on the 45-hectare site. The internal utility network is 90 per cent complete and the road network 80 per cent, with around 3,000 people working on the construction site every day. The first production equipment arrived this summer.

“In January 2027 we would already be starting to install the production lines,” said Ádám Kovács. Trial operation is planned for the second to third quarter of 2027. More than 400 permits are needed for operation, and 270–280 of them are already in place. The plant is being built for a capacity of 28 GWh and will produce 46-series cylindrical cells for BMW.

The investment in figures

The investment is worth almost HUF 400 billion, or EUR 1 billion. State support amounts to HUF 13.8 billion, around 3.45 per cent of the total cost. In return, the company has committed to HUF 730 billion in additional revenue and HUF 32 billion in additional wage payments by 2033.

EVE Power Hungary currently employs 517 people, 90 per cent of them Hungarian. The target is around 1,000 employees. 150 Hungarian subcontractors are working on the project, and the number of Hungarian business partners has grown almost fivefold to around 200. Between 2023 and 2025, the company paid EUR 258 million to Hungarian companies.

Water: from greywater, without groundwater

The plant has been permitted to use around 3,300 cubic metres of water a day, 85 per cent of it greywater. The city will build the greywater pipeline in 2027. The company may not use groundwater, not even during trial operation.

Dialogue with the city

“It is not enough for us to inform the city. We also have to listen to it,” said Dániel Kiss. The company’s environmental permit is public, and anyone can read it on the company’s new website. EVE has also promised independent, accredited measurements and neighbourhood focus groups.

Partnerships have also grown beyond business. An agreement with VOSZ, the National Association of Entrepreneurs and Employers, helps small and medium-sized enterprises become suppliers. In education, the company works with the Debrecen Vocational Training Centre, the University of Debrecen and Wuhan University, and in sport it supports the DVSC women’s handball team.